|
To
View And Print Out This Document Click Here
*Microsoft Word Format*
Follow these guidelines
for safe installation of Wood Trusses.
These guidelines should not be considered to be the only method
for erecting and bracing of a roof system. WWTA disclaims any responsibility
for damages arising from the use, application or reliance on these
guidelines.
1. Check Trusses, while
they are on the ground.
- a)
Count trusses to ensure that you have the correct number
for the job.
b)
Measure trusses for the correct pitch, span and any special
details.
c)
Check for damage, broken members, loose plates, etc
2. Erection Procedure
a)
Mark the bearing plates on both walls to the required spacing
of trusses,
(Normally 24” O/C).
b)
Hoist the trusses to the roof level, taking care not to
bend or twist the trusses.
c)
If interior walls are available, trusses may be laid flat.
d)
If no partitions exist, trusses shorter than 32’ may be
inverted and hung from the bearing plates.
e)
Erect Gable or End trusses and install braces to prevent
lateral movement,
(See Figure below).
f)
Run a string from heel to heel of the end trusses to be
used as a guide line.
g)
Erect trusses using string to locate heels. Brace each
truss as it is erected.
h)
Trusses may be marked at one end. Place trusses so that
all marked ends are on the same side of the building.
i)
When flat trusses are used, ensure that they are installed
with the proper side up.
j)
Install temporary bracing with sufficient X-bracing
to prevent trusses from buckling or toppling over. Install permanent
bracing.
k)
Complete roof by installing roof decking, gable end ladders,
etc.

Always provide horizontal restraint
for the Top Chords
3. Handling Recommendations
Trusses must be in the vertical plane to
take advantage of their superior ability to support loads.
 
The truss erector or the builder shall
take the necessary precautions to ensure that erection procedures
and handling methods do not damage the trusses and thus reduce their
load carrying capacity.
4. Mechanical Handling
Ideally when mechanical means are used,
the trusses should be lifted in banded sets and lowered onto supports.
When this method is used, extreme caution
must be exercised when breaking the metal straps. Trusses may dominoe,
lose lateral stability, or totally collapse, if temporary braces
and supports are not in place before releasing the banding.
Lifting
trusses singly should be avoided, but if necessary an appropriate
spreader bar should be used with slings of sufficient strength and
placed in a “toed-in” position. The “toed-in” position will prevent
the truss from folding.
If erectors have any doubt,
contact the truss supplier immediately.

For spans of 20 feet or less, a single pick up point may be used to lift
the truss. A tag line should be used whenever a truss is lifted
to avoid having it swing and do damage.
 
Trusses up to 30 feet in length should be lifted using two pick up points
located so that the distance between them is approximately one-half
the length of the truss. The angle between the two cables should
be 60 degrees or less to reduce the tendency for the truss to buckle
laterally during the lift. A tag line should be fastened to one
end to prevent the truss from swinging and causing damage to other
parts of the work or to the truss itself.
 
A spreader bar and short cable slings should be used to lift trusses in
the 30 to 60 foot range. The cable slings may be vertical but it
is recommended that they be “toed-in” to prevent the truss from
folding during the lift. Two tag lines should be used to control
the raining of trusses of this size.
 
Trusses above 60 feet in length should be lifted with a strongback 2/3
to 3/4 the length of the truss. The truss should be securely tied
to it at 10 foot intervals or less. For flat trusses, the strongback
should be tied to the top chord. Pitched trusses should be positioned
high enough on the strongback to prevent overturning of the truss.
Two tag lines should be used to control the truss during lifting.
5. Vertical and Lateral Alignment
ALL TRUSSES ARE LATERALLY UNSTABLE
until properly braced. The longer
the span the more care required. Adequate restraint is necessary
at all stages of construction.
COMPLETE STABILITY is not achieved until the bracing and decking is completely
installed and properly fastened.
ERECTION, BRACING AND PROCEDURES as well as the safety of the workers are the responsibility
of the erector.
PROBLEMS MAY OCCUR in attempts to realign trusses. Align each truss and
place it permanently in position before it is connected to the bracing
system. Once there is a load, even from the weight of the truss
itself, large lateral forces are developed by attempts to realign
the trusses. This may break the bracing system.
 
|
When properly aligned, each top chord should not
vary more than 1/2 inch from a straight line.
|
Out-of-plumb installation tolerances |
 |
 |
| THE BRACING SYSTEM
should provide support at spacings no farther apart than the
drawing shown for the bridging. Without Proper bracing trusses
may not support even their own weight |
COLLAPSE CAN EASILY
OCCUR without a bracing system that will prevent both horizontal
sway (pictured to the left) or roll over (pictured above). By
rolling on their sides, where they have no strength, the trusses
will break or pull the ends off the bearings |
DO NOT permit cutting, drilling or any procedure that may
damage the chords or webs.
DO NOT remove webs (even temorarily).
DO NOT make field repairs to damaged trusses without the
approval of the manufacturer.
DO NOT overload single or groups of trusses with plywood,
roofing or other construction materials or tools.
DO NOT erect damaged trusses. Should a truss or group of
trusses fall to the ground or be damaged what so ever, do not proceed!
Thesite engineer of note must certify that the trusses are satisfactory
to erect. Notify the truss supplier immediately.
6. Temporary Gable End and
Top Chord Bracing
7. Laminating Girders
All girder trusses that require laminating; two plys or more, must be
laminated according to the instructions on the truss design drawings
or as per Appendix B, Tables B.1.1, B.1.2, B.1.3, B.1.4 and B.1.5
of TPIC Truss Design Procedures manual.

8. Permanent Bracing Specified
by the Building Designer
Permanent bracing is designed and specified for the structural safety
of the building. It is the responsibility of the building designer
or an authority other than the truss designer to indicate size,
location and attachments for all permanent bracing. Typical applications
of permanent bracing to be specified by the building designer are
as follows:
a) Top
chord bracing:
If purlins are used, it is recommended that diagonal bracing be applied
to the underside of the top chord as shown below.

b)
Bottom chord bracing:
This lateral and diagonal bracing is required to maintain the proper truss
spacing and to transfer force due to lateral forces into the side
walls, shear walls or other resisting structural elements.

c)
Diagonal web bracing:
The diagonal web bracing specified by the building designer is used to
hold the trusses in a vertical position, to maintain the proper
spacing, to distribute unequal loading to adjacent trusses and to
transfer lateral forces to the diaphragms and shear walls.

d)
Anchoring of permanent lateral web bracing:
Permanent lateral bracing similar to that described in Section 9 must
be anchored. It is the responsibility of the building designer to
specify the type of anchor. A typical method of anchoring the permanent
lateral web bracing is illustrated below.

9. Permanent Lateral Bracing
Specified by the Truss Designer

a)
All permanent lateral
bracing shown on the truss design drawing must be of the size and
grade as specified and must be fastened at the locations shown using
the number and size of nails as specified on the truss design drawing.
b)
Lateral movement
of the lateral bracing shall be restrained by permanently installing
cross bracing (as shown in Section 8d) at the ends of each truss
run and at intervals not exceeding 20 feet or as shown on the structural
drawings.
c)
If it is not possible
to install permanent lateral web bracing as specified on the truss
design drawing or if the truss run is less than three trusses of
the same kind, a “T” brace shall be installed as per the truss design
drawing or Appendix C, Table C.1.1, of the TPIC Truss Design Procedures
manual.
10. Top
Chord Sheathing Plane
a)
If plywood sheathing is used, it must be applied with staggered joints and adequate nailing.
b)
If purlins are used,
spacing should not exceed the design buckling length of the top
chord and should be adequately attached to the top chord.
c)
If Valley Sets, Conventional Framing, Piggyback Trusses,
etc., are installed on top of the
main trusses, the full length of the top chords of these trusses
must be restrained by sheathing or purlins spaced as specified on
the structural or truss design drawings. Top chords of trusses must
always be restrained from lateral movement.
|